Time and Work Questions and Answers

Time and Work Questions  

Time and Work Question and Answers are provided on this page for students to practice and get an idea about  how this topic is asked in placement  exams.

time

The fundamental questions that could be asked in the exam regarding the issue of Time and Work are listed below:

  1. Familiarize yourself with the fundamental  concepts of time and work, such as how to calculate work done and time taken.
  2. Understand the basic Formula,  Work = Rate x Time.
  3. Reciprocal Work Rate: Learn how to deal with situations where a person’s work rate is given in terms of the time taken to complete the work (e.g., “Raj can do a job in 10 days,” which means Raj’s work rate is 1/10 of the job per day).
  4. Practice problems involving multiple individuals working together or at different rates to complete a task.
  5. Fractional Work: Learn how to handle cases where a fraction of work is completed (e.g., “A completes half the work”).
  6. Work Efficiency: Understand the concept of efficiency and how it relates to work rates.-

Rules on Time and Work

  • Let’s consider  M1 number of individuals are able to complete W1 amount of work within D1 days whereas M2 number of individuals  are able to complete W2 amount of work in D2 days, then the formula used will be:
    M1\times \frac{D1}{W1} = M2 \times \frac{D2}{W2}
  • If the individuals are having productivity of E1 and E2 individually, then the formula used to calculate the same will be:
     M1\times D1\times T1\times \frac{E1}{W1} =M2\times D2\times T2\times \frac{E2}{W2}
  • If person A is able to do a part of work in ‘n’ number of days, then the work done by A in a single day is equals to
     \frac{1}{n}
  • If person X might complete an amount of work in D1 number of days as well as person Y is able to complete the similar amount of work in D2 number of days then person X and person Y together can do the similar type of work in:
    \frac{D1\times D2}{D1\ + D2}
  • Considering that person X is twice efficient worker as person Y, then person X would be taking half of the time occupied by person Y to do a similar amount of work.
  • If person X along with person Y can together complete a part of work in D1 number of days as well as person X unaccompanied is able to complete it in D2 number of days, then person Y can alone complete the work in:
    \frac{D1\times D2 }{D2 – D1}

Prime Course Trailer

Related Banners

Get PrepInsta Prime & get Access to all 200+ courses offered by PrepInsta in One Subscription

Also Check Out

1. Sam can finish a task is 12 days, and Adam can finish it in 15 days. Calculate how much time together they will take to complete the same job?

20 / 3

20 / 3

87.15%

16 / 3

16 / 3

4.67%

9 / 2

9 / 2

5.55%

18 / 7

18 / 7

2.63%

Sam’s 1 day effort = 1/12

Adam’s 1-day effort = 1/15

1 day effort of both of them = 1/12 + 1/15 = 3/20

Therefore, together they can finish the task in = 20/3 days

Hence Option A is the correct one.

2. Max and Samantha can together finish the project in 12 days. If Samantha alone takes 30 days to complete, then calculate the days in which Max will finish the project alone?

25

25

5.49%

20

20

88.35%

16

16

3.99%

19

19

2.17%

Max and Samantha together work time = 12

Max and Samantha one-day effort = 1/12

Samantha’s one-day effort = 1/30

Max one day effort = 1/12 – 1/30 = 1/20

Therefore, Max will take 20 days to finish the project.

Hence Option B is the correct one.

3. George and Victor can finish making a painting in 12 hours, Victor and Sam in 15 hours, Sam and George in 20 hours. Find in how many hours will they together finish the painting?

21

21

5.04%

10

10

81.39%

21/2

21/2

9.98%

11

11

3.59%

George and Victor, one hour work, = 1/12

Victor and Sam one hour work = 1/15

Sam and George one hour work = 1/20

George, Victor, and Sam’s one hour work = (1/2)(1/12 + 1/15 + 1/20) = 1/10

Therefore, George, Victor, and Sam can finish the painting in 10 hours.

4. Mary is three times as good as Jonny. If they finish a task together in 15 days, calculate the days taken by Mary alone to complete the work.

20

20

75.86%

25

25

7.89%

30

30

11.52%

17

17

4.73%

One day work by Mary: One day work by Jonny = 3:1

(Mary + Jonny)it's one-day work = 1/15

Now, when we divide 1/15 in the ratio of 3:1

Therefore, Mary’s one day work = (1/15) x (3/4) = 1/20

Hence, Mary can alone finish it in 20 days.

5. M can do a task in 25 days, and S can finish a similar job in 20 days. They work as one for five days and M goes away. Calculate the days required by S to do the work then?

12

12

8.68%

11

11

75.05%

17

17

7.18%

21.5

21.5

9.09%

M and S 5 days’ work = 5(1/25 + 1/20) = 9/20

Work left= 1 – 9/20 = 11/20

Now, 1/20 work is finished by S in 1 day.

Therefore, 11/20 work will be finished by S in 11 days

6. Max can finish writing one chapter in 2 days. While Alex can do the same chapter in 5 days, calculate the number of days taken them together to complete the chapter?

5/9

5/9

2.19%

1/2

1/2

2.92%

10/7

10/7

93.81%

8/11

8/11

1.08%

Time taken by Max = 2 days

The effort did by Max in one day = 1/2

Days have taken by Alex = 5 days

The effort did by Alex in one day = 1/5

Thus, together they can complete work = (1/2) + (1/5) =7/10

Therefore, time required 10/7 days

 

7. Jack is three times as good as Rose. Jack can finish a task in 60 days less than Rose. Calculate the time in which they can complete the job together.

\frac{43}{3}

\frac{43}{3}

10.63%

\frac{45}{2}

\frac{45}{2}

77.22%

\frac{47}{2}

\frac{47}{2}

7.26%

\frac{49}{2}

\frac{49}{2}

4.9%

Let us assume that Rose can do the job in x days.

Then, Jack can do the job in (x -60) days.

Therefore, time taken by Jack = times of Rose/3

Therefore, x-60 =x/3

=>3x – 180 = x

=>x = 90 days

Time taken by Rose = 90 days

Time taken by Jack = 30 days

Therefore, Rose and Jack’s one day work =(30 + 90)/(30 x 90) = 2/45

Hence, they can complete the same work together in  45/2 days.

Therefore option B is the correct one.

8. Mike and Nik can finish a project in 45 days and 40 days individually. Both of them started the project together, but Mike quits subsequently by some days, and Nik finishes the outstanding in 23 days. Find in how many days Mike quits?

8/3

8/3

10.74%

7/2

7/2

10.92%

9

9

69.37%

9/5

9/5

8.98%

Nik’s work after Mike quits = 23 * 1/40 = 23/40

Outstanding work = 1 – 23/40 = 17/40

Mike and Nik’s one day effort = 1/45 + 1/40 = 17/360

Therefore, 17/360 work done by Mike and Nik is one day

Thus, 17/40 work is done by Mike and Nik in = (360/17) * (17/40) = 9 days

Hence Option C is the correct one.

9. Jack and Vinny can finish their target in 12 days. Vinny and Sid together can complete the goal in 15 days. If Jack is twice as good as Sid, calculate the number of days required by Vinny alone to finish the target?

21

21

7.68%

22

22

10.98%

25/2

25/2

11.08%

20

20

70.26%

Let the one day work by jack is “x” ,sid is '2x’ and that of vinay be’v’

2x+v = 1/12……………..(1)

v+x = 1/15…………….(2)

Now, from (1) - (2) we get

X = 1/60

There for

v=1/12 – 1/30

= 1/20

The no of days = 20

10. Ross and Sam can finish an assignment in 15 days together. Ross can complete this Assignment alone in 20 days. Calculate the days taken by Sam to do the same assignment alone?

25

25

4.52%

60

60

87.98%

30

30

5.24%

33

33

2.26%

Ross and Sam’s one day’s effort =1/15

Ross’s one day’s effort =1/20

Therefore, Sam’s one day’s effort = (Ross and Sam)’s one day’s effort- Ross’s one day’s effort

=1/15 - 1/20 = 1/60

Hence, Sam can finish the Assignment in 60 days

Therefore option B is the correct one.

×

Please login to report

Also Check Out

Get over 200+ course One Subscription

Courses like AI/ML, Cloud Computing, Ethical Hacking, C, C++, Java, Python, DSA (All Languages), Competitive Coding (All Languages), TCS, Infosys, Wipro, Amazon, DBMS, SQL and others

Checkout list of all the video courses in PrepInsta Prime Subscription

Checkout list of all the video courses in PrepInsta Prime Subscription