Quants Menu9>
- HCF and LCM
- Number System
- Number Decimals & Fractions
- Surds and Indices
- Divisibility
- Ages
- LCM
- HCF
- Inverse
- Speed Time and Distance
- Work and Time
- Boats and Streams
- Pipes and Cisterns
- Averages
- Allegations and Mixtures
- Ratio and Proportions
- Simple & Compound Interest
- Simple Interest
- Compound Interest
- Percentages
- Profit & Loss
- Successive Discount 1
- Successive Discount 2
- AP GP HP
- Arithmetic Progressions
- Geometric Progressions
- Harmonic Progressions
- Probability
- Permutation & Combination
- Combination
- Circular Permutation
- Geometry
- Heights and Distances
- Perimeter Area and Volume
- Coordinate Geometry
- Venn Diagrams
- Set Theory
- Algebra
- Linear Equations
- Quadratic Equations
- Logarithms
- Clocks
- Calendars
- Clocks and Calendars
- Finding remainder of large powers
PREPINSTA PRIME
Formulas For Time and Work
Time and Work Formulas
Go through the entire page to know easy Formulas For Time and Work that will help you to solve problems quickly.
Formula's For Time and Work
Work from Days:
If A can do a piece of work in n days, then A’s one day work = \frac{1}{n}
Days from work:
If A’s one day work = \frac{1}{n}, then A can finish the work in n days
Work Done by A and B
A and B can do a piece of work in ‘a’ days and ‘b’ days respectively.
When working together they will take \frac{ab}{a+b} days to finish the work
In one day, they will finish \frac{a+b}{ab} part of work.
Ratio:
If A is thrice as good a workman as B, then:
Ratio of work done by A and B = 3: 1.
Ratio of times taken by A and B to finish a work = 1: 3
Efficiency:
Efficiency is inversely proportional to the
Time taken when the amount of work done is constant.
Efficiency α = \frac{1}{Time Taken}
Rules for Time and Work
Rule 1: If A completes a piece of work in x days. And B can completes same piece of work in y days .
Then,
One day work of A = \frac{1}{x} One day work of B = \frac{1}{y}
Work done by A + B = \frac{1}{x} + \frac{1}{y} = \frac{x+y}{xy}
Total time = \frac{xy}{x + y}
Rule 2: If A completes a piece of work in x days. B completes same piece of work in y days .C completes same piece of work in z days
Then,
One day work of A = \frac{1}{x}
One day work of B = \frac{1}{y}
One day work of C = \frac{1}{z}
Work done by A + B + C = \frac{1}{x} + \frac{1}{y} + \frac{1}{z} = \frac{yz+xz+xy}{xyz}
Total time = \frac{xyz}{xy + yz + zx}.
Rule 3: If M1 men can complete a work W1 in D1 days and M2 men can complete a work W2 in D2 days then, \frac{M_{1}D_{1}}{W_{1}} = \frac{M_{2}D_{2}}{W_{2}} .
If Time required by Both M1 and M2 is T1 and T2 respectively, then relation is \frac{M_{1}D_{1}T_{1}}{W_{1}} = \frac{M_{2}D_{2}T_{2}}{W_{2}}
Rule 4: If A alone can complete a certain work in ‘x’ days and A and B together can do the same amount of work in ‘y’ days,
Work done by b =\frac{1}{y} – \frac{1}{x} = \frac{x-y}{xy}
Then B alone can do the same work in \frac{xy}{(x-y)} days
Rule 5: If A and B can do work in ‘x’ days.
If B and C can do work in ‘y’ days.
If C and A can do work in ‘z’ days.
Work done by A,B and C = \left ( \frac{1}{2}\right )\left ( \frac{1}{x}+\frac{1}{y}+\frac{1}{z} \right )
Total time taken when A, B, and C work together \frac{2xyz}{ ( xy+yz+zx )}
Rule 6: Work of one day = \frac{Total work}{Total number of working days}
Total work = one day work × Total number of working days
Remaining work = 1 – work done
Work done by A = A’s one day work × Total number of working days of A
Rule 7:If A can finish \frac{m}{n} part of the work in D days.
Then total time taken to finish the work by A = \frac{D}{\frac{m}{n}} = \frac{n}{m} × D days
Rule 8:
If A can do a work in ‘x’ days
B can do the same work in ‘y’ days
When they started working together, B left the work ‘m’ days before completion then total time taken to complete the work = (y+m)x/(x+y)
Rule 9: A and B finish work in a days.
They work together for ‘b days and then A or B left the work.
B or A finished the rest of the work in ‘d’ days.
Total time taken by A or B alone to complete the work = \frac{ad}{a – b} or \frac{bd}{a-b}
Questions based on above formulas:
Question 1: A construction crew of 8 workers can build a house in 24 days. How many days will it take for 12 workers to build the same house?
Answer: Let the amount of work required to build the house be represented as “1 house.”
8 workers can build the house in = 24 days
Day taken by 12 workers to build the house = \frac{8 \times 24}{12}
= {8 \times 2}
= 16 days
Question 2: A bakery can bake 180 cakes in 6 days. How many cakes can it bake in 10 days?
Answer: Let the amount of work required to paint the house be represented as “1 house.”
Time taken by 15 painters to paint a house = 9 days
Time taken by 9 painters to paint the same house =
\frac{15 \times 9}{9}
= {15 \times 1}
= 15 days
Question 4: A machine can produce 240 widgets in 5 days. How long will it take for the machine to produce 600 widgets?
Question 5 : If a team of 6 workers can complete a project in 18 days, how many workers are needed to complete the project in 9 days?
Prime Course Trailer
Related Banners
Get PrepInsta Prime & get Access to all 200+ courses offered by PrepInsta in One Subscription
Also Check Out
Get over 200+ course One Subscription
Courses like AI/ML, Cloud Computing, Ethical Hacking, C, C++, Java, Python, DSA (All Languages), Competitive Coding (All Languages), TCS, Infosys, Wipro, Amazon, DBMS, SQL and others
- Speed Time and Distance – Questions | Formulas | How to Solve Quickly | Tricks & Shortcuts
- Boats and Streams – Questions | Formulas | How to Solve Quickly | Tricks & Shortcuts
- Pipes and Cisterns – Questions | Formulas | How to Solve Quickly | Tricks & Shortcuts
- Speed Time and Distance –
Questions |
Formulas |
How to Solve Quickly |
Tricks & Shortcuts - Boats and Streams –
Questions |
Formulas |
How to Solve Quickly |
Tricks & Shortcuts - Pipes and Cisterns –
Questions |
Formulas |
How to Solve Quickly |
Tricks & Shortcuts
Login/Signup to comment