TCS Time and Work Questions Quiz 1

Question 1

Time: 00:00:00
Thomas takes 7 days to paint a house completely whereas Aashay require 9 days to paint the same house completely. how many days will take to paint the house if both them work together?

3.9

3.9

2

2

5

5

3

3

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 2

Time: 00:00:00
Jake can dig a well in 16 days. Paul can dig the same well in 24 days. Jake, Paul and Hari together dig the well in 8 days. Hari alone can dig the well in?

48 days

48 days

24 days

24 days

27 days

27 days

36 days

36 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 3

Time: 00:00:00
A alone can do 1/4th of the work in 2 days. B alone can do 2/3th of the work in 4 days. If all the three work together, they can complete it in 3 days so what part of the work will be completed by C in 2 days?

1/20

1/20

1/12

1/12

1/8

1/8

1/16

1/16

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 4

Time: 00:00:00
A certain sum of money is sufficient to pay either George wages for 15 days or Mark wages for 10 days .For how long will it be sufficient if both George and Mark work together ?

5 days

5 days

6 days

6 days

8 days

8 days

9 days

9 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

PrepInsta User

Atleast check the language of questions Question language is so wrong

Question 5

Time: 00:00:00
Babla alone can do a piece of work in 10 days ashu alone can do it in 15 days. The total wages for the work in Rs.5000 . How much should babla be paid of they work together for entire duration of the work?

5000

5000

4000

4000

3000

3000

2000

2000

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 6

Time: 00:00:00
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

15 days

15 days

20 days

20 days

12 days

12 days

9 days

9 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 7

Time: 00:00:00
4 men can check exam papers in 8 days working 5 hours regularly. What is the total hours when 2 men will check the double of the papers in 20 days?

9 hours

9 hours

4 hours

4 hours

8 hours

8 hours

none

none

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

PrepInsta User

As we know , M1*D1*W2=M2*D2*W1 So here M1 =4 D1=8DAYS*5HOURS=40 W2 =2 M2=2 D2=20DAYS *xhours Substituting the values in formula 4*40*2=2*20x*1 160*2=40x 320/40=x So x=8 hours

Question 8

Time: 00:00:00
George does 3/5th of a piece of work in 9 days. He then calls Paul. and they finish the work in 4 days. How long would Paul take to do the work by himself?

30 days

30 days

35 days

35 days

32 days

32 days

28 days

28 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 9

Time: 00:00:00
Y can do a work in 2/3 the time it takes x, z can do same work in ¾ time it takes y. when all three are typing the same time what is the fraction of total work does y do?

1/3

1/3

8/29

8/29

4/13

4/13

9/23

9/23

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 10

Time: 00:00:00
The ratio of efficiency of A is to C is 5:3.The ratio of no.of days taken by B is to C is 2:3.A takes 6 days less than C, when A and C completes the work individually.B and C left the work after 2 days. the no of days taken by A to finish the remaining work?

28/3

28/3

5

5

6

6

4.5

4.5

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

PrepInsta User

A : B : C Efficiency 10 : 9 : 6 No of days 9x : 10x : 15x given=> 15x-9x = 6 hence, x = 1 Number of days taken by A = 9 and daily work done=10 Number of days taken by B= 10 and daily work done=9 (total work =90) Number of days taken by C = 15 and daily work done=6 work done by B and C in initial 2 days =30 rest work =60 Number of days required by A to finish = 60/10=6 days

["0","40","60","80","100"]
["Need more practice! \r\n \r\n","Keep trying! \r\n \r\n","Not bad! \r\n \r\n","Good work! \r\n \r\n","Perfect! \r\n \r\n"]

Personalized Analytics only Availble for Logged in users

Analytics below shows your performance in various Mocks on PrepInsta

Your average Analytics for this Quiz

Rank

-

Percentile

0%

Get over 200+ Courses under One Subscription

mute

Don’t settle Learn from the Best with PrepInsta Prime Subscription

Learn from Top 1%

One Subscription, For Everything

The new cool way of learning and upskilling -

Limitless Learning

One Subscription access everything

Job Assistance

Get Access to PrepInsta Prime

Top Faculty

from FAANG/IITs/TOP MNC's

Get over 200+ course One Subscription

Courses like AI/ML, Cloud Computing, Ethical Hacking, C, C++, Java, Python, DSA (All Languages), Competitive Coding (All Languages), TCS, Infosys, Wipro, Amazon, DBMS, SQL and others.

Comments