EFFICIENCY OF A AND C = 5:3 (RATIO OF WORK DONE AND EFFICIENCY IS JUST REVERSE)
RATIO OF WORK DONE = 3:5 (LET IT BE 3X : 5X)
GIVEN :DIFFERENCE BETWEEN A\'s AND C\'s WORK DONE IS 6 DAYS SO, 5X-3X=6, X=3;
SO, A DO WORK IN 3*3= 9 DAYS
C DO WHOLE WORK IN=5*3=15 DAYS
NOW RATIO OF WORK DONE OF B AND C IS 2:3 (LET IT BE 2X : 3X)
AS WE HAVE CALCULATED C\\\\\\\'S TOTAL WORK DONE IN 15 DAYS SO, 3X=15 DAYS , X=5
THEN B\\\\\\\'S TOTAL WORK DONE IS 2*5= 10 DAYS
NOW WE HAVE TOTAL WORK DONE BY A ,B AND C IN 9,10 AND 15 DAYS RESPECTIVELY
B ANC WORK FOR 2 DAYS MEANS (1/10 +1/15)*2=1/3
REMAINING WORK=1-1/3 = 2/3
A DO TOTAL WORK IN 9 DAYS SO, 2/3 WORK IS DONE IN (9*2/3)=6 DAYS