First Naukri Time and Work Quiz -1

Question 1

Time: 00:00:00
Prerana, Ranit, and Soumyo, three teammates, can create a robot in six days for their university tech fest. Prerana completes the same task in 15 days less than Ranit. Determine how many days Soumyo would need to complete the job alone at 75% of his original productivity if Ranit can finish it in 35 days.

240/23

240/23

540/21

540/21

560/37

560/37

None of these

None of these

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 2

Time: 00:00:00
Rina, Mina, and Sita, three painters, complete a masterpiece in six days for which they are paid Rs. 480. Find Mina's daily income if her productivity, Mina's productivity, and Sita's efficiency are in the ratio 4: 5:7.

30

30

50

50

35

35

25

25

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 3

Time: 00:00:00
Farhana and Sulagna can create a wall hanging in three days, which is 12 days faster than if they worked jointly. Determine when Farhana would be able to complete the wall hanging by herself.

10

10

12

12

18

18

9

9

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 4

Time: 00:00:00
There are three employees. Irfan, Modi, and Obama have each been assigned a mission. They began the job together, but Obama quit after three days, when just 37% of the work was completed. Irfan and Modi finished the remaining work in seven days. Irfan and Modi have a 4 to 5 performance ratio. Find the number of days the slowest worker would need to finish the job on their own.

30

30

12

12

15

15

22

22

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 5

Time: 00:00:00
A community of team leaders agreed to complete a campaign in four days, but 20 men left each day. If the job was done in seven days, how many men originally agreed to do it?

132

132

140

140

121

121

114

114

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 6

Time: 00:00:00
Raja and Akash, two male colleagues, can complete a portion of their project in 20 and 35 hours, respectively. Raima can finish task by herself in H hours, at a third of her original performance. Find the value of H if all three people working together at their normal productivity will finish the job in 6 hours.

331/23

331/23

560/37

560/37

783/2

783/2

None of the above

None of the above

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 7

Time: 00:00:00
Abhishek can complete a project in 20 days, while Rishikesh can complete it in 12 days. If they start working together on prime number dates on April 29th, when will they finish the work?

12th may

12th may

5th may

5th may

17th may

17th may

None of these

None of these

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 8

Time: 00:00:00
Arnab would take three times as long as Arun and Ashish combined to complete a final year project, and Ashish would take four times as long as Arun and Arnab combined. The mission can be completed in 5 days if all three of them work together. How long does it take Arnab and Ashish to finish the project?

99/4

99/4

100/9

100/9

131

131

152/5

152/5

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 9

Time: 00:00:00
In 15 days, Arpan can complete 3/5 of a project. Bikash has a 25 percent greater performance than Arpan. Both Arpan and Bikash began working jointly and left five days later. Chandra finished the rest of the work in 11 days. Is Chandra's productivity higher or lower than Arpan's?

Higher

Higher

Lower

Lower

Same

Same

Cannot be determined

Cannot be determined

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

Question 10

Time: 00:00:00
Jay and Ria can finish a project individually in 10 and 12 days. Jay started working alone, and after 4 days, Ria joined him. Calculate the time taken by them to complete the work .

7.2727

7.2727

9.3762

9.3762

13.245

13.245

None of these

None of these

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Start

["0","40","60","80","100"]
["Need more practice!","Keep trying!","Not bad!","Good work!","Perfect!"]

Personalized Analytics only Availble for Logged in users

Analytics below shows your performance in various Mocks on PrepInsta

Your average Analytics for this Quiz

Rank

-

Percentile

0%

Completed

0/10

Accuracy

0%

Prime

Prime Mock

Complete Prime Mock Subscription for First Naukri

For First Naukri
Get Prime Mock
Get Prepinsta Prime

Get all 200+ courses offered by Prepinsta

Never Miss an OffCampus Update

Get OffCampus Updates on Social Media from PrepInsta

Follow us on our Media Handles, we post out OffCampus drives on our Instagram, Telegram, Discord, Whatsdapp etc.

Get Hiring Updates
Amazon,Google,Delottie & 30+companies are hiring ! Get hiring Updates right in your inbox from PrepInsta

Get over 200+ course One Subscription

Courses like AI/ML, Cloud Computing, Ethical Hacking, C, C++, Java, Python, DSA (All Languages), Competitive Coding (All Languages), TCS, Infosys, Wipro, Amazon, DBMS, SQL and others.

Get over 200+ course One Subscription

Courses like AI/ML, Cloud Computing, Ethical Hacking, C, C++, Java, Python, DSA (All Languages), Competitive Coding (All Languages), TCS, Infosys, Wipro, Amazon, DBMS, SQL and others.

Get PrepInsta Prime Subscription

Get access to all the courses that PrepInsta offers, check the out below -

Companies

TCS, Cognizant, Delloite, Infosys, Wipro, CoCubes, KPMG, Amazone, ZS Associates, Accenture, Congnizant & other 50+ companies

Programming

Data Structures, Top 500 Codes, C, C++, Java Python & other 10+ subjects

Skills

Full Stack Web Development, Data Science, Machine Learning, AWS Cloud, & other 10+ skills and 20+ projects

Comments