Question 1

Time: 00:00:00
Rita , Gita and Sita can do a piece of work in 24 days , 20 days and 15 days respectively. If they got total wages of rs. 3800, then find the difference between the wages got by Sita and Gita.

 

 

500

500

800

800

480

480

400

400

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 2

Time: 00:00:00
To finish a work, A sets aside half additional time than B. In the event that together they take 18 days to finish the work, what amount of time might B take?

 

30 days

30 days

35 days

35 days

40 days  

40 days  

45 days

45 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 3

Time: 00:00:00
Anand finishes a work in 7 days, Bittu finishes the same job in 8 days and Chandu in 6 days. They take turns to finish the work. Anand on the first day, Bittu on the second and Chandu on the third day and then Anand again and so on. On which day will the work get over?

 

3  

3  

7

7

9

9

6

6

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 4

Time: 00:00:00
Billy is four times as good a workman as Silly and can build a wall in 45 days less than the number of days required by Silly. What is the time they will take, working together, to build two such walls?

 

12 days

12 days

24 days

24 days

9 days  

9 days  

18 days

18 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 5

Time: 00:00:00
To do a Project, Badal would take three times as long as Abhishek and Chitra together and Chitra twice as long as Abhishek and Badal together. All three working together on the Project can complete in 10 days. How long would Abhishek take by himself to complete the same Project?

20 days  

20 days  

24 days

24 days

40 days

40 days

60 days

60 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 6

Time: 00:00:00
At their usual efficiency levels, Manish and Naman together build a wall in 12 days. If Manish had worked half as efficiently as he usually does, and Naman had worked thrice as efficiently as he usually does, the wall would have been built in 9 days. How many days would Manish take to build the wall if he works alone at his usual efficiency?

18 days

18 days

36 days

36 days

24 days

24 days

12 days

12 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 7

Time: 00:00:00
Three Friends worked together for 30 days on a project, all of them remained absent for few days. Ayush was absent for 10 days more than Harsh and Deep did one-third of the total work. How many days more than Deep, Ayush was absent?

4  

4  

5

5

6

6

Cannot be determined

Cannot be determined

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 8

Time: 00:00:00
Priyanshu can do a piece of work in 50 days. He worked only for 5 days and was infected with Covid-19 and had to leave the job. Ashish completed the remaining work in 30 days. The number of days in which Priyanshu and Ashish together can complete the work?

22

22

20  

20  

25

25

27

27

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 9

Time: 00:00:00
Mohan is four times as good a workman as Rishikesh and can build a Building in 45 days less than the number of days required by Rishikesh. What is the time they will take working together to build two such buildings?

12

12

24

24

9

9

18

18

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

Question 10

Time: 00:00:00
Shekhar can paint a wall in 10 days. Vishal can do it in 12 days and Bipul can do in 15 days. All begin together but Shekhar leaves the work after 2 days and Vishal leaves 3 days before the painting is finished. How long did it take to complete the paint the whole wall?

5 days

5 days

9 days

9 days

4 days  

4 days  

7 days

7 days

Once you attempt the question then PrepInsta explanation will be displayed.

Please login to submit your explanation

["0","40","60","80","100"]
["Need more practice!","Keep trying!","Not bad!","Good work!","Perfect!"]

Personalized Analytics only Availble for Logged in users

Analytics below shows your performance in various Mocks on PrepInsta

Your average Analytics for this Quiz

Rank

-

Percentile

0%

Get over 200+ Courses under One Subscription

mute

Don’t settle Learn from the Best with PrepInsta Prime Subscription

Learn from Top 1%

One Subscription, For Everything

The new cool way of learning and upskilling -

Limitless Learning

One Subscription access everything

Job Assistance

Get Access to PrepInsta Prime

Top Faculty

from FAANG/IITs/TOP MNC's

Get over 200+ course One Subscription

Courses like AI/ML, Cloud Computing, Ethical Hacking, C, C++, Java, Python, DSA (All Languages), Competitive Coding (All Languages), TCS, Infosys, Wipro, Amazon, DBMS, SQL and others.